Title: Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
Authors: LEŚNIAK, A., PISKORZ, G., SPIŠÁKOVÁ, M., MAČKOVÁ, D.
Keywords: construction works, delays factors, contractors, questionnaire survey
Abstract: Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One attempt was to identify and assess the potential causes of delays in the construction works resulting from the provisions of the contract. The knowledge of these factors can help contractors to take protective measures, reducing the risk of delays during the implementation of construction works.
DOI: 10.22630/PNIKS.2018.27.1.7
APA style references: Leśniak, A., Piskorz, G., Spišáková, M. & Mačková, D. (2018). Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia. Scientific Review Engineering and Environmental Sciences, 27 (1), 71-81. doi: 10.22630/PNIKS.2018.27.1.7
APA style citation in text: The first time citation in text: (Leśniak, Piskorz, Spišáková & Mačková, 2018), next citation: (Leśniak et al., 2018)
Chicago style references: Leśniak, Agnieszka, Grzegorz Piskorz, Marcela Spišáková, Daniela Mačková. "Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia." Scientific Review Engineering and Environmental Sciences, 79 ser., vol. 27, no 1, (2018): 71-81. doi: 10.22630/PNIKS.2018.27.1.7.
Chicago style citation in text: (Leśniak et al. 2018)
Bibtxt style references: Bibtxt_utf8_79art7en.bib
More citations in MLA, Harvard, RIS e.t.c styles in
CrossRef database: Actions/Cite
Full text PDF (in English)