Title: How to calculate dates and slack time in PDM diagram with different relationship types between tasks

Authors: POŁOŃSKI, M.

Keywords: Precedence Diagramming Method (PDM), relationship, activity dates, critical paths

Abstract: This article aims to present method of calculating dates and slack time in PDM diagrams with different types of relationships between tasks. Algorithms that have been worked out by the Author as well as enclosed computational example enable to analyze a process of determining these values. Knowledge of adopted algorithms facilitates accurate interpretation of calculation outcomes and improved construction of relationship networks for users of computer programmes. These two crafts are ultimately fundamental for planning and realization management of engineering objects.

APA style references: Połoński, M. (2010). How to calculate dates and slack time in PDM diagram with different relationship types between tasks. Scientific Review Engineering and Environmental Sciences, 19 (2), 60-74.

APA style citation in text: The first time citation in text: (Połoński, 2010), next citation: (Połoński, 2010)

Chicago style references: Połoński, Mieczysław. "How to calculate dates and slack time in PDM diagram with different relationship types between tasks." Scientific Review Engineering and Environmental Sciences, 48 ser., vol. 19, no 2, (2010): 60-74.

Chicago style citation in text: (Połoński 2010)

Bibtxt style references: @article{Połoński_2010_PNIKS, author={Połoński, Mieczysław}, title={How to calculate dates and slack time in PDM diagram with different relationship types between tasks.}, journal={Scientific Review Engineering and Environmental Sciences}, URL={http://iks_pn.sggw.pl/PN48/A5/art5.pdf}, year={2010}, volume={19 (2)}, number={48}, pages={60-74}}

Full text PDF


Go Back